· SW19 · standard spec
ConfirmedNet cost (ex. O&P)
£52,478.55
Overhead + profit (22.0%)
£11,545.29
Quote ex. VAT
£64,023.84
Saved 20:59
- Velux loft
- 8 × 5 m (40.0 m²) · 2.4 m high
- Bedroom
- 4 × 3.5 m (14.0 m²)
- Bathroom
- 2.5 × 2 m (5.0 m²)
- Property type
- Detached
- Property age
- 1920-1944
- Spec tier
- Standard
- Postcode
- SW19
- Property Age
- 1920-1944
- Ground Type
- Sandy Gravel
- Planning
- Permitted Development
48 line items · 21 ancillary
| # | Task | Unit | Qty | Labour | Material | Total | Note | |
|---|---|---|---|---|---|---|---|---|
| 1 | Loft | £9,438.02 | ||||||
| 2 | Structural | £884.43 | ||||||
| 3 | Carpentry | £5,442.31 | ||||||
| 4 | Services | £4,298.57 | ||||||
| 5 | Finishes | £5,522.74 | ||||||
| 6 | Decoration | £1,470.57 | ||||||
| 7 | Flooring | £4,608.76 | ||||||
| 8 | Joinery | £191.95 | ||||||
| 9 | Facilitating Works | £557.66 | ||||||
| 10 | Bathroom | £6,424.11 | ||||||
| 11 | Preliminaries & Site Setup | £8,978.74 | ||||||
Risk Notes
- ▸Labour hours are based on standard industry productivity rates and assume competent, uninterrupted working. They exclude allowances for adverse weather, material-delivery delays, restricted access beyond that noted, and below-standard productivity.
- ▸The programme assumes a standard working week of 40 hours per operative (Monday to Friday; weekends and public holidays excluded) with a gang of 2. A 27% buffer and fixed curing / drying periods are already included for typical real-world delays.
- ▸This is a cost estimate, not a fixed-price quotation or a guaranteed programme. Actual hours, duration and cost may vary with site conditions, design development and specification changes.
- ▸Inter-war (1920-1944): early cavity walls with galvanised wall ties prone to corrosion. Suspended timber floors common; ventilation under-floor should be checked. Original window frames often single-glazed.
- ▸Detached: no party wall constraints. Good site access assumed.
- ▸Sandy gravel: good free-draining ground. Standard 1.0m depth sufficient.
- ▸Works within Permitted Development. Confirm PD not removed by Article 4. Consider Lawful Development Certificate.
- ▸Engineered timber floor in a bathroom: not waterproof and not the manufacturer-recommended floor finish for wet rooms. Steam and standing water can damage the wear layer over time; tile, safety vinyl or glue-down LVT are the standard recommendations. Confirm the homeowner explicitly chose this finish and is comfortable with the maintenance / warranty implications.